Location: Crowland. Peterborough
Contract Duration: 12 Weeks

This was a demolition of a 19th century former primary school in Peterborough.
Licensed and Non-Licensed asbestos removal, demolition, slab and foundation removal and on site crushing.
We completed the job in 12 weeks using our specialised plant such as our JS330, JS220, Telehandler and Crusher.
A.R.T. Demolition was contracted to carry out this sensitive demolition.
We had to dig anti-vibration trenches and monitor vibration with sensors around the site.